Has anyone tried to import a Project Libre file in BBIM? I exported a simple file as .xml (attached as .txt) but on importing it as Microsoft Project (.xml)
I had this error:
, thanks
Has anyone tried to import a Project Libre file in BBIM? I exported a simple file as .xml (attached as .txt) but on importing it as Microsoft Project (.xml)
I had this error:
, thanks
Have you tried exporting/importing it with open source alternatives?
@Coen said:
Have you tried exporting/importing it with open source alternatives?
I just used Project Libre to create a couple of tasks and saved it as .xml
please advise if there are other options, thanks
Supporting LibreOffice is on the to-do list but hasn't been requested so far. Can you open your .xml in MSP or P6 and then save again in the mean time?
@SigmaDimensions said:
Supporting LibreOffice is on the to-do list but hasn't been requested so far. Can you open your .xml in MSP or P6 and then save again in the mean time?
Thanks for your reply
unfortunately I no longer have MSP on my laptop, I was trying to replace it with ProjectLibre (I wasn't aware of LibreOffice being able to do work scheduling, any advice?)
Sorry I meant ProjectLibre.
You can use a .csv import if it's not something too complex. Here's a template.
I'll do a basic implementation of ProjectLibre .xml during the christmas break now that there's a need for it :)
@SigmaDimensions said:
Sorry I meant ProjectLibre.
You can use a .csv import if it's not something too complex. Here's a template.
I'll do a basic implementation of ProjectLibre .xml during the christmas break now that there's a need for it :)
Nice, I tried and it works just fine, thanks a lot for your support, always very much appreciated !
PS it would be handy if importing schedule (Cost or Work) were to be available directly from Costing and Scheduling, like with Resources ;)
@SigmaDimensions said:
Sorry I meant ProjectLibre.
You can use a .csv import if it's not something too complex. Here's a template.
I'll do a basic implementation of ProjectLibre .xml during the christmas break now that there's a need for it :)
sorry, how do you set in the .csv multiple predecessor/successor? sometimes the same task can trigger more than one successor
It can be done in the UI, I was wondering if it was also possible in the .csv (I tried few combinations but did not work)
thanks
Try splitting with a semi colon:
11FS12 ;11SS13
@SigmaDimensions said:
Try splitting with a semi colon:
11FS12 ;11SS13
yep, that did the trick, thanks for your quick response, appreciated.
@SigmaDimensions said:
Sorry I meant ProjectLibre.
You can use a .csv import if it's not something too complex. Here's a template.
I'll do a basic implementation of ProjectLibre .xml during the christmas break now that there's a need for it :)
oddly when I import a .csv work schedule (attached as .txt file) I cannot have the summary tasks updated in the UI
when I generate the Gantt summary dates look OK but their duration is not showing
but no problem if I do it manually (everthing from start to end, no .csv import), I also notice they have a duration with a P prefix and an *
both cases I used the same calendar / duration / relatationships, and entered the first date in the same task (1.1.1 Ground slab)
is there a particular sequence to follow when importing data from .csv to have summary tasks updated?
Thanks
a even weirder workaround is to export it as P6.xml and import it back, all summary tasks are correctly showing their dates and duration..
oddly when I import a .csv work schedule (attached as .txt file) I cannot have the summary tasks updated in the UI
Should now be fixed for csv imports.
Also made sure derived durations are shown as human readable.
Cheers @steverugi
@SigmaDimensions said:
oddly when I import a .csv work schedule (attached as .txt file) I cannot have the summary tasks updated in the UI
Should now be fixed for csv imports.
Also made sure derived durations are shown as human readable.
Cheers @steverugi
Thank you!