current:
I have a simple BoQ and a linked Schedule of Rates
question 1:
is there any way to add a column in the BoQ to show the code from the SoR?
I thought the Schedule Columns
could be the way to go but it doesn't seem to do much
by the way, if I randomly add a column it creates one in the BoQ and the SoR, once added it cannot be removed by pressing the X
next to it.
question 2:
is Schedule Columns
a feature meant for future developmnent or has alrady some functionality in the available Cost Schedule?
many thanks in advance for your assistance