by MahdiA2024 on 30 May 2024, edited 31 May 2024
#
Hi
In the Construction Scheduling tab, I created Work Calendars. I added a weekly time schedule for Monday, Tuesday, Wednesday, Thursday, and Friday.
I started adding a few tasks and created a timeline for the tasks:
Schedule Start: 01.05.2024
Schedule Finish: 08.05.2024
Schedule Duration: 8 days
The duration is shown as 8 days, but the correct duration should be 6 days because my working week excludes weekends (i.e., Saturday and Sunday). This means two days should be subtracted from the 8 days, but this adjustment has not happened. Can anyone help me? I want to know the solution for calculating the duration without weekends. Is this duration correct, or is there a programming problem or an unknown solution?


S
by steverugi on 31 May 2024, edited 31 May 2024
#
+1 votes
@MahdiA2024 said:
Hi
In the Construction Scheduling tab, I created Work Calendars. I added a weekly time schedule for Monday, Tuesday, Wednesday, Thursday, and Friday.
I started adding a few tasks and created a timeline for the tasks:
Schedule Start: 01.05.2024
Schedule Finish: 08.05.2024
Schedule Duration: 8 days
The duration is shown as 8 days, but the correct duration should be 6 days because my working week excludes weekends (i.e., Saturday and Sunday). This means two days should be subtracted from the 8 days, but this adjustment has not happened. Can anyone help me? I want to know the solution for calculating the duration without weekends. Is this duration correct, or is there a programming problem or an unknown solution?
make sure the calendar is properly stored

and assigned to the work schedule by clicking on the grid symbol


as you can see my end date is as expected (10/5/24)